Bathrooms and kitchen are now complete…

OK, so there is still some painting to do but the main work has completed 🙂

See the final image from the ground floor toilet:

Day 18 - Ground Floor Bathroom

We managed to get the first coat of the paint on the kitchen walls last night, with the hope that the second (and final) coat will go on tonight.  Then, the kitchen and utility rooms will be finished completely.  The ground floor toilet will need a coat of paint at some point sadly – the wall got damaged during the previous unit removal 🙁

We also have a carpet to be fitted to the stairs and upstairs hallway soon – just waiting to hear when te fitter can get to us 🙂

The outside tap got fixed today as well so Simon can get back onto cleaning the cars given that a) the tap is now fixed and b) the weather has warmed up a bit 🙂